All the aspects of design and construct process was undertaken by Pentamec. We were able to complete the project way ahead of the schedule as our production was completed from our Factory, Installation was done from the site which led to sufficient space utilization for other firms to complete their work as well as a part of the Crusher. This played a major role in completion of the whole project before schedule.
Major aspects of this project
This building is equipped with up to 20 TON overhead crane.
This building has 53 feet height for the manufacturing process of the Crusher.
All Accessories such as Wall, Gable, Corner flashing and extensive use of color added an extract attraction to the project.